How to choose a fit-out or finishing contractor in Egypt

Choose a finishing or fit-out company in Egypt on evidence, not on the lowest total. Verify its commercial register, tax card and contractors' federation membership, ask for an itemised BOQ (مقايسة) priced against the same scope as the other bidders, and sign a written Arabic contract with milestone payments, a programme and the warranty the law already gives you.

Last updated:
Reviewed by Eng. Ahmed Shalaby, Founder & Chairman, Shalaby Enterprises

Key points

  • Check papers first: commercial register, tax card and membership of the Egyptian Federation for Construction and Building Contractors.
  • Send every bidder the same drawings, specification and BOQ, then compare quotes line by line, not by price per square metre.
  • Pick the contract type on purpose: lump sum, re-measured BOQ or cost-plus each moves risk to a different party.
  • By law a finishing provider must guarantee its work for at least one year, and structural defects carry ten-year liability.

Should I hire a finishing company or individual tradesmen?

Hire a company when you want one party responsible for programme, quality and the interfaces between trades. Hire tradesmen (صنايعية) directly only if you, or an engineer you pay, can coordinate the sequence and inspect each stage yourself.

Finishing is a chain of dependent trades, from rough-ins and plaster to flooring, paint and final fixtures; with separate agreements, every delay becomes yours to coordinate. The table is general guidance, not a ranking.

QuestionFinishing / fit-out companyIndividual tradesmen
Who is responsible for the result?One contractor, under one contractEach tradesman for his own trade only
Paperwork and receiptsShould issue a contract, BOQ and receipts in ArabicOften verbal; you must insist on writing
Best suited toFull apartments, villas, offices, shops, clinicsSmall, single-trade jobs you can supervise

How do I check that a finishing company is legitimate in Egypt?

Ask for three documents before you discuss price: the commercial register showing contracting activity, a valid tax card, and the company's membership card with the Egyptian Federation for Construction and Building Contractors.

  1. Commercial register (السجل التجاري). The activity should include contracting or finishing. The federation itself asks for this document, a valid tax card and other papers before it registers a contractor.
  2. Tax card (البطاقة الضريبية). It must be valid.
  3. Federation membership (Law 104/1992). Law 104 of 1992 created the federation. Article 7 prohibits assigning or carrying out contracting work above EGP 50,000 per contract to a non-member, and Article 46 sets a fine of EGP 1,000–10,000 with cancellation of the contract. These 1992 amounts may since have been amended; ask to see the membership card.
  4. Grade (الفئة). Members are classified, in some specialties from first (highest) to seventh grade, by capital, staff, turnover and experience. A grade reflects size, not quality.
  5. Relevant record. Ask for projects of a similar type and size, with locations you can visit and a client you can call.
  6. Who does the work. Which trades are in-house and which are subcontracted, including doors, joinery and MEP?

What questions should I ask a finishing company at the first meeting?

Ask questions whose answers you can later write into the contract.

  1. Will you price my BOQ item by item, with assumptions and exclusions in writing?
  2. Which contract type do you propose, and why?
  3. Who is the site engineer, and how often will I get progress reports with photos?
  4. Does the programme allow for plaster curing and the bathroom flood test?
  5. What warranty do you give beyond the legal minimum?

What is a finishing BOQ (مقايسة تشطيب), and how do I compare quotes line by line?

A bill of quantities, or مقايسة, lists every work item with its unit, quantity and specification, so that each contractor prices exactly the same thing. It is the only fair basis for comparing offers.

A single price per square metre hides what is inside it: contractors use the same level names for different specifications.

Free apartment finishing BOQ template (copy into Excel)

Keep the items that apply, add quantities from your drawings, and send the same sheet to every bidder with rates left blank. Items follow the usual finishing order.

No.Item and what to specifyUnitQtyRate (EGP)Amount (EGP)
AElectrical
1Electrical rough-in: conduits, boxes, cables (brand, cross-section)point
2Distribution board and breakersno.
3Switches and sockets (brand, range)no.
BPlumbing and waterproofing
4Plumbing rough-in: supply and drainage (pipe system)point
5Waterproofing of wet areas, incl. 48-hour flood testm²
6Sanitary ware and mixers, supply and fix (brand, model)no.
CWalls and plaster
7Internal red-brick walls, if not builtm²
8Internal plaster, incl. curingm²
DFloors and tiling
9Floor porcelain or ceramic (size, grade, brand)m²
10Wall tiles, bathrooms and kitchenm²
11Skirtingm
ECeilings and paint
12Gypsum-board ceilingsm²
13Gypsum cornicesm
14Paint, walls and ceilings (brand, coats)m²
FDoors, windows and AC
15Internal doors with frames and hardwareno.
16Windows, UPVC or aluminiumm²
17AC copper pipework and drainsm
GGeneral
18Debris removal and final cleaninglot
Exclusions, stated in writing: kitchen, AC units, appliances, light fittings

To use it in Excel or Google Sheets, select the table (or press the button) and paste. Add a formula so that Amount = Qty × Rate, and a total at the bottom. A villa needs extra lines for roofs, stairs and facades.

How to compare quotes:

  • Mark any item a bidder left out, priced as "provisional", or changed in specification. A cheap total often comes from missing lines.
  • Compare the exclusions lists: who supplies sanitary ware, kitchen, AC units, lighting fixtures? Who removes debris?
  • Ask each bidder to explain rates that are far from the others. A rate well below the rest is either a different specification or a future variation.
  • Only then compare totals, payment terms and programme.

For what drives the total, see our guide to apartment and villa finishing cost in Egypt; for what "lux" or "super lux" should mean in a BOQ, see finishing levels in Egypt.

Design-and-build company or finishing-only contractor?

Choose a design-and-build company (a "decor and finishing" company, شركة ديكورات وتشطيبات) if you want one party responsible from drawings to handover. Choose a finishing-only contractor if you already have drawings from an independent designer and want several firms to price the same BOQ.

Design and buildFinishing only, separate designer
ResponsibilityOne contract for design and works; fewer gaps between drawings and siteDesigner answers for the drawings, contractor for the works
Price comparisonHarder: design choices and prices come from the same firmEasier: every bidder prices the same drawings and BOQ
ChecksAsk who reviews quality on your sideThe designer can inspect the contractor's work
Design feeOften inside the total; ask for it as a linePaid separately; typically 150–500 EGP per m²

Either way, insist on full drawings and a written specification before pricing. A design-and-build offer without drawings is a price for an unknown scope.

Lump sum, re-measured or cost-plus: which finishing contract should I sign?

Use a lump sum when the design and specification are complete, a re-measured BOQ when quantities may change, and cost-plus only when you can audit costs closely. Each type decides who carries the risk of quantities and prices.

TypeHow the price worksWho carries the riskWorks best when
Lump sum (مقطوعية)One fixed price for a defined scopeContractor carries quantity risk; you carry the risk of an unclear scope (variations)Drawings and specification are final
Re-measured BOQ (بالمقايسة / بالحصر)Fixed unit rates; final quantities measured on siteShared: rates are fixed, quantities are notExisting units, renovations, quantities not yet certain
Cost-plusActual cost of materials and labour plus an agreed fee or percentageMostly you; the final total is openUrgent or design-as-you-go work with full cost transparency

Whatever the type, attach the signed BOQ and specification. The consumer protection law requires contracts, invoices and receipts in legible Arabic.

What should a finishing contract (عقد تشطيب) include?

A finishing contract should fix the scope, price, programme, payments, variations, delay terms, handover standard and warranty in writing, with the BOQ and specification attached.

  • Scope: drawings, BOQ and specification as annexes; a written exclusions list.
  • Price and contract type: lump sum, re-measured or cost-plus, and what is included in the price.
  • Programme: start date, completion date, key stages and inspection points.
  • Payments: advance, milestone payments tied to finished stages, final payment on handover.
  • Materials: brands and grades, sample approval, what happens if a brand is unavailable.
  • Variations: no extra work without a signed variation order with price and time impact.
  • Delay: what applies if the contractor finishes late and how extensions are granted.
  • Handover and snagging: how snags are listed and closed, documents handed over.
  • Warranty: period and scope, no shorter than the legal minimum.

The consumer protection regulations also require finishing and home-installation providers to issue a receipt before work starts, and to state the service details, timing and total price.

How should payments to a finishing contractor be staged?

Pay an advance on signing, then pay each instalment only after a stage is finished and inspected, and keep a final payment until handover.

There is no official "standard" percentage. A common Egyptian turnkey structure is 10% on signing, then milestone payments of 5–10% each for rough-ins, plaster, tiling, paint, fixtures and doors, and 10% on handover.

StagePay afterInspect before paying
SigningContract, BOQ and programme signedReceipt issued
Rough-insElectrical and plumbing first fix completeRoutes match drawings; pressure test on pipes
PlasterPlaster completeLevels and corners; curing done
Waterproofing and flooringWet areas sealed, floors laidFlood test passed; tile levels and joints
Fixtures and doorsFinal fix completeEverything operates
HandoverSnags closed, documents deliveredSigned handover record

Many clients also agree a retention held until snags are closed; the amount is for negotiation.

What warranty does Egyptian law give on finishing work?

Under Consumer Protection Law 181 of 2018, Article 26, a provider of finishing, maintenance and home installation services must guarantee the work for at least one year, or at least three years if the defect results from fraud or gross negligence.

  • Receipt before work: the Executive Regulation (Prime Minister's Decision 822/2019), Article 20, requires finishing and home-installation providers to issue a receipt before starting; without one, the consumer may prove the terms by any evidence.
  • Structural defects: Civil Code Article 651 makes the architect and contractor jointly liable for ten years from delivery for total or partial collapse and for defects that threaten stability. Article 653 voids any clause excluding or limiting this, and under Article 654 claims lapse three years after the collapse or the discovery of the defect. This matters if your works touch walls, slabs or structure, not for cosmetic finishes.

Your contract can give you more than the law, never less. Complaints go to the Consumer Protection Agency, which received 16,415 in October 2026 alone, so keep your documents organised.

Does interior finishing need a permit in Egypt, and what about compound rules?

Building Law 119 of 2008, Article 39, requires a licence to build, extend, raise, modify, reinforce, restore or demolish, and to carry out external finishing. The law gives no explicit exemption for purely internal, non-structural finishes, so treat any structural change or external work as needing a licence, and ask a qualified engineer about your case.

Buildings with five or more units must have an Occupants' Union (Article 72), which is responsible for common parts and the building's architectural character (Article 75); decisions of its general assembly bind all members (Article 81). Compounds add their own developer or union regulations on working hours, deliveries, debris and facade changes. Get those rules in writing before the contractor's programme is fixed.

Finishing in New Cairo and 6th of October compounds

There are no single rules for all compounds in New Cairo (the Fifth Settlement) or 6th of October; each developer or occupants' union sets its own. Before you sign, ask compound management in writing for: working hours and days, entry permits for workers and vehicles, any refundable deposit or insurance against damage, delivery and debris routes, and rules on facades, balconies and AC outdoor units. Attach them to the contract and make the contractor responsible for following them.

What does fit-out mean for offices, shops and clinics?

Fit-out (فيت أوت) means turning a built space into a usable interior: partitions, ceilings, floors, MEP, finishes and joinery. Commercial projects add landlord rules, fire and life-safety systems, and tighter programmes.

Landlords describe the starting point as shell and core (structure and risers only), Category A (a basic landlord finish) or Category B (the tenant's own layout and branding). Definitions differ, so write the landlord/tenant boundary into your BOQ. See our MEP and ELV contracting page and fit-out contractor in Egypt.

What are the red flags when choosing a finishing contractor?

Slow down or walk away if you see any of these:

  • A price far below the others with no explanation of scope.
  • No site visit before pricing, or a single "price per metre" with no BOQ.
  • Reluctance to put exclusions, the programme or the warranty in writing.
  • Large payments requested ahead of progress, or cash without a receipt.

Printable checklist: before you sign a finishing contract

Print or save as PDF, and tick each line for every bidder.

  • Commercial register (contracting activity) and valid tax card seen
  • Federation membership card and grade seen
  • Two or more similar projects visited or verified, one client reference called
  • Site visit and measurement done before pricing
  • Same drawings, specification and BOQ sent to every bidder
  • BOQ priced item by item; assumptions and exclusions written
  • Programme in sequence with inspection points
  • Payments tied to finished, inspected stages; final payment at handover
  • Warranty at least the legal minimum; snagging and handover documents defined
  • Contract, BOQ and receipts in Arabic; receipt issued before work starts

How Shalaby Enterprises works

SH Spaces handles residential finishing for apartments and villas, including apartment and villa renovation and interior design. Shalaby Contracting takes commercial, hospitality and administrative fit-out as main or package contractor, prices against your BOQ, and sources doors and joinery from its sister factory, Shalaby Industries. Our project record runs from Cairo and 6th of October to Damietta port and Saint Catherine in South Sinai.

Frequently asked questions

How do I choose the best finishing company in Egypt?

Shortlist companies that can show a commercial register, a valid tax card and contractors' federation membership, plus similar projects you can verify. Send all of them the same drawings, specification and BOQ, compare the offers line by line, and choose the one whose scope, programme, payment terms and warranty are complete and written, not simply the lowest total.

Should I hire a finishing company or individual tradesmen?

A company gives you one party responsible for the programme, quality and the interfaces between trades, under one contract. Individual tradesmen can cost less, but you or an engineer you pay must coordinate the sequence, inspect each stage and keep the paperwork. For a full apartment, villa or office, most clients are better served by one contractor.

What is a cost-plus finishing contract compared with lump sum?

In a lump sum (مقطوعية) contract you pay one fixed price for a defined scope, and the contractor carries the quantity risk. In cost-plus you pay the actual cost of materials and labour plus an agreed fee, so the final total stays open and you carry most of the risk. Cost-plus needs full access to invoices and close auditing.

How do I prepare a BOQ (مقايسة) for my apartment?

List every work item in the order it is built, from rough-ins and plaster to flooring, ceilings, paint, fixtures and doors. For each item state the unit, the quantity measured from drawings or on site, and the specification, including brand and grade. Leave the rates for contractors to fill in, so that every offer prices the same thing.

Does interior finishing need a permit in Egypt?

Building Law 119 of 2008, Article 39, requires a licence for construction, modification, reinforcement, demolition and external finishing. The law text has no explicit exemption for purely internal, non-structural finishes, so treat structural changes and external works as licensed works, check your compound's rules, and ask a qualified engineer about your specific case.

What warranty must a finishing contractor give in Egypt?

Consumer Protection Law 181 of 2018, Article 26, requires finishing and home-installation providers to guarantee their work for at least one year, or at least three years for fraud or gross negligence. For collapse or defects that threaten stability, Civil Code Article 651 sets ten-year liability that a contract clause cannot exclude.

Are there finishing companies that offer payment in instalments?

Some companies advertise instalment plans. Whatever the plan, read who finances it, the total you pay over time and what happens if work stops. The safest structure is still an advance on signing, then payments only after finished and inspected stages, with a final payment held until handover and snagging are complete.

Should I hire a design-and-build (decor and finishing) company?

A design-and-build company handles drawings and works under one contract, which reduces gaps between design and site. The trade-off is that prices are harder to compare, because the same firm sets the design and the price. If you want competitive bids, get drawings from an independent designer and send the same BOQ to several finishing contractors.

How do finishing companies price a job: per m² or by BOQ?

Many advertise a price per square metre for a named level, such as lux or super lux. A fair offer, though, is a priced BOQ: each item with its unit, quantity, specification and rate, plus written exclusions. Ask for the BOQ even if you start from a per-m² figure. Our finishing cost guide lists typical 2026 ranges.